Completed Projects

Railway Lines



  Project Name        Reconstruction of Northern Railway Reconstruction Projects - Medawachchiya to Madu Road
  Location within Country Northern Province
  Start Date (Month/Year)  March 2011
  Completed Date  (Month/Year) May 2013
  Client  Sri Lanka Railways  

Description of Project :

The main scope of work is re-construction of 63Km of track from Maduroad to Thalaimannar Pier and 5 station yards with platforms, 3 sub-stations with platforms, 66 culverts, 5 bridges and 34 level crossings. The design speed of the train is 120 kmph. The track structure will be with long welded joints, switch expansion joints (SEJ) and glued insulated joints on concrete sleepers.

Description of Services Provided:

Culvert-68,
Bridge-11,
Level crossing-21